Queensland Curtis LNG (QCLNG) – Upstream Trunk Line Project
Construction of various Steel Water pipelines, Gas pipelines and various other infrastructure.
- Date: Completed
- Client: QGC – A BG Group Business
- Project Type: Construction
Project Value: Upon request
About this Project
EDA were engaged to provide Superintendent and Construction Management Services to the Queensland Curtis LNG (QCLNG) Upstream Trunk Line Project and the scope consisted of:
- Construction of approximately 112 km of High Voltage Cables (HVC) and 160 km Fiber Optic Cables (FOC).
- Construction of approximately 88 km Steel Water pipeline with diameters ranging between 350mm-960mm including installation of Back Pressure Control Valves, Flow meters and Telemetry Units
- Construction of approximately 74 km gas pipelines with diameters ranging between 350mm-500mm including pig receiving facilities.
The above Gas infrastructure will connect QGC’s Field Compressor Stations and Central Processing Plants. Water pipelines will transport production water from gas hubs to QGC’s Water Treatment Plants.
Queensland Curtis LNG
Key Achievements
Successfully –
- Completed water pipeline construction with in the agreed time frames
- Completed water pipeline without any safety incidents
- Completed water pipeline without any LTI’s or MTI’s
- Mitigated construction risks by pro-actively planning the construction tasks
- Completed water pipeline construction with minimal impact to Environment and Fauna
- Completed water pipeline construction without any NCR’s or Infringement Notices from the authorities
- Ensured that the water pipeline constructed met the specifications and standards
- Ensured that the water pipeline constructed to the agreed Quality standards
- Ensured that the Contractor was always in compliance with all the approved Plans and Procedures including but not limited to:
- Construction Management Plan (Clear and Grade, Stringing, Welding, Trenching, Lowering and Backfill )
- Safety Management Plan
- Environment and Fauna Management Plan
- Cultural Heritage Management Plan
- Traffic Management Plan
- Fatigue Management Plan
- Hydro test Management Plan
Contact Us
BRISBANE | MELBOURNE | MILDURA | SHEPPARTON | MORANBAH | CHARTERS TOWERS
0431 601 947
reddy.eda@edapm.com.au
Brisbane Office
0405 724 484
Shop 20, KP Shopping Centre,
SHAILER PARK QLD 4128
Melbourne Office
0431 601 947
1 Queens Road
MELBOURNE VIC 3000
Shepparton Office
0481 081 650
70 New Dookie Rd
SHEPPARTON VIC 3630