7th Street Road Refurbishment (WTP)

Refurbishment and resurfacing works on Seventh street (near WTP) in the region of Mildura council.

  • Date: Completed June 2020
  • Client: Lower Murray Water
  • Project Type: Construct
    Project Value: Upon request

About this Project

The scope of this project was to carry out various refurbishment and repair works on Seventh Street (WTP).  The civil works carried out as part of the project included, but were not limited to:

  • Earthworks;
  • Subgrade preparation;
  • Crushed rock pavement layers;
  • Asphalt pavement layers;
  • Storm water and subsurface drainage including pipes and pits;
  • Concrete works including spoon drains, kerbing and plinth;
  • Keystone retaining wall.

As a part of the engagement, EDA was responsible for providing the below services – 

  • Project Management
  • Issue and evaluation of tenders.
  • Appointment and mobilization of successful contractor.
  • Responsible for Contract management,  Project Closure, Final Payments and Defects liability.

    Lower Murray Water

    Key Challenges & Achievements

    • Project delivered within the program approved budget and time.
    • Project delivered amidst COVID-19 pandemic with all relevant government regulations and precautions.
    • Timely assessment of submitted progress claims and notices to contractor processed.
    • No safety incident or any environmental incidents.
    • No damage to the third party assets.
    • No disruption or loss to Client’s operations or customers.

    Contact Us

    7 + 6 =

    BRISBANE | MELBOURNE | MILDURA | SHEPPARTON | MORANBAH | CHARTERS TOWERS

    0431 601 947

    reddy.eda@edapm.com.au

    Brisbane Office

    0405 724 484

    Shop 20, KP Shopping Centre,

    SHAILER PARK QLD 4128

    Melbourne Office

    0431 601 947

    1 Queens Road

    MELBOURNE VIC 3000

    Shepparton Office

    0481 081 650

    70 New Dookie Rd

    SHEPPARTON VIC 3630